Factsheet: Small scale grid connection RD 1699/2011

Small scale grid connection RD 1699/2011

Key Information
Full name of Instrument & Measure (English): 
Royal Decree-Law 1699/2011, dated 18 November, regulating the grid connection of small-scale power plants
Full name of Instrument & Measure (native language): 
Real Decreto 1699/2011, de 18 de noviembre, por el que se regula la conexión a red de instalaciones de producción de energía eléctrica de pequeña potencia
Description: 
RD 1699/2011 establishes the basic administrative conditions, contractual, economic and technical for the connection of small-scale power plants to the electricity distribution network
Goal/Aim: 
Stimulate electricity generation from small-scale plants and regulate their connection to the grid

Sector/Topic targeted:

Status:

Year Instrument & Measure Started: 
2011